Rio Grande Valley Broadband • Entered by Susan Ostlie on September 29, 2019

Strategy meeting and Forest Plan meeting

September 26, 2019

Participants and Hours

Pre Planning hours 1
Post Admin hours 1
Activity Hours 4
Participants 3
Total Hours 14

Key Issue: Landscape-level Planning
Activity Type: Advocacy (rallies, lobbying, meeting decision makers, letters/calls/emails)
Key Partners: NMWA, Sierra Club, NM Native Plant Society,
Landscape/area: Cibola National Forest (1616435 acres)

Short Description of Activity

I met with lawyers from NMWA and members of the Sierra Club to plan the wilderness strategy for advocating for recommended wilderness. Then we also went to the final public meeting of the Cibola NF for the Plan Revision process.

Reflection/Evaluation

Goal was to get answers about where in the plan to find comparisons for different management strategies. I did get some answers.