Central Oregon Bitterbrush Broads • Entered by Mary Fleischmann on October 15, 2021
Road monitoring- Mill Creek
October 4, 2021
Participants and Hours
Pre Planning hours | 4.75 |
Post Admin hours | 6.5 |
Activity Hours | 9.75 |
Participants | 8 |
Total Hours | 89.25 |
Key Issue: Multiple apply
Activity Type: Stewardship (monitoring, sampling, planting, etc.)
Key Partners: Land Watch; Advocates for the West
Short Description of Activity
Completion of the earlier started Forest Service Road Monitoring in the MIll Creek area of the Ochoco’s.
Reflection/Evaluation
Everyone had a good time and had a team of 4 teams of 2 people….Able to look at 40 – 50 roads and so completed 80% of the remaining work from previously.